Initial Drive and Short-Term Restrike • 23 piles tested during initial drive • 15 piles tested during just a single restrike (between 1 and 9 days) > 20 bpi on restrike • 3 SLT piles did not have short term restrikes • 5 piles had multiple short term restrikes as initially planned (probably not necessary) • High variability in set-up magnitude, across the site, and within same pier